Virtual Power Purchase Agreements in India: What CERC's 2025 VPPA Guidelines Mean for Corporate Renewable Energy Strategy

CERC Introduces a Regulatory Framework for Virtual Power Purchase Agreements
For the better part of a decade, corporate India's appetite for renewable energy has run ahead of the contracts available to satisfy it. Companies wanted the price certainty and the green credentials of a long-term power purchase agreement, without the balance-sheet commitments of physical wires, dedicated transmission capacity, or proximity to a generator. The instrument the rest of the world calls a virtual power purchase agreement, a financial hedge dressed up as a power contract, has existed in term sheets and board presentations for years before it existed in Indian law.
That gap has now closed. The Central Electricity Regulatory Commission (“CERC”) has finalised India's regulatory framework for virtual power purchase agreements (“VPPAs”) through the Guidelines for Virtual Power Purchase Agreements (“VPPA Guidelines” or “Guidelines”), notified on December 24, 2025 and followed by a statement of reasons dated April 27, 2026 (“SOR”). The Guidelines have been issued under Regulation 54(3) of the CERC (Power Market) Regulations, 2021, will take effect from a date to be separately notified, and follow the draft guidelines circulated for public consultation on May 22, 2025 (“Draft Guidelines”).
For corporate consumers, the Guidelines provide long-awaited regulatory certainty. They confirm that a company can hedge its renewable energy costs through a VPPA with a renewable energy project located anywhere in India, without physically purchasing or consuming the electricity generated by that project. At the same time, the Guidelines prescribe a detailed compliance framework governing the structure and operation of such arrangements. This piece examines the key requirements under the Guidelines, the regulatory objectives they seek to achieve, and the practical implications for renewable energy developers.
What is a Virtual Power Purchase Agreement?
A Virtual Power Purchase Agreement is a financial settlement contract between a renewable energy generating station (“REGS”) and a consumer, under which no electricity physically moves from the generator to the consumer at all. The REGS sells its actual output on a power exchange as ordinary, unlabelled ‘brown power’. The environmental value of that generation- its ‘greenness’, travels separately to the consumer as renewable energy certificates (“RECs”). Underneath both flows sits a straightforward contract for difference: the consumer and the generator agree a strike price in advance, and whichever way the market price on the exchange moves, the difference is settled bilaterally between them. The structure does two things that a physical PPA cannot do alone. It converts a volatile input cost into a fixed one, without the connectivity and balance-sheet commitments of a physical wire. It also converts a compliance obligation into a bankable and tradable asset in the form of RECs, creating a framework around which transaction structures, risk allocation mechanisms, and contractual protections can be built. That combination is precisely why VPPAs have become the instrument of choice for corporates with net-zero commitments but no physical footprint anywhere near a wind or solar site.
The Regulatory Origins of the VPPA Guidelines
The emergence of a formal VPPA framework in India was closely linked to the broader question of regulatory oversight for electricity-linked derivative products. The Committee on Efficient Regulation of Electricity Derivatives recommended that non-transferable specific delivery (“NTSD”) contracts fall within CERC's regulatory domain, while other electricity derivatives be regulated by SEBI. In Power Exchange India Ltd. v. SEBI, the Supreme Court recorded and gave effect to the agreed position between the regulators, thereby providing judicial recognition to this division of regulatory oversight.[6] In 2025, SEBI further clarified that VPPAs are non-tradable and non-transferable over-the-counter (“OTC”) arrangements that do not fall within the scope of the Securities Contracts (Regulation) Act, 1956. Against that backdrop, the Ministry of Power requested CERC to formulate a dedicated VPPA framework[9] culminating in the issuance of the Guidelines. The resulting framework places VPPAs firmly within the sphere of electricity regulation. Consistent with that approach, the Guidelines repeatedly emphasise that VPPAs must remain non-tradable and non-transferable, reinforcing their character as bespoke contractual arrangements rather than market-traded financial instruments.
Who Can Enter into a VPPA and Who Cannot
Eligibility under the Guidelines is drawn narrowly, and deliberately so. On the buy side, the counterparty must be a ‘consumer’ under the Electricity Act, 2003 or a ‘designated consumer’ (“DC”) under the Energy Conservation Act, 2001, in other words, an entity already inside India's regulatory perimeter for either electricity supply or energy-intensive consumption. On the sell side, the counterparty must be a REGS.
The SOR confirms that all REGS projects are eligible, including those with energy storage systems and hybrid generating stations, a welcome preservation of technology neutrality for developers betting on storage-backed capacity. Both new and existing RE projects are covered, and pre-existing contracts may qualify if restructured and duly registered, though CERC has foreclosed one obvious workaround: conversion of an existing physical power purchase agreement into a VPPA is not envisaged. Foreign entities that do not consume electricity in India, international RECs, and other environmental attribute certificates all fall outside the framework.
The Seven Pillars of VPPA Compliance
Beyond defining what constitutes a VPPA, the Guidelines establish a broader compliance framework governing REC eligibility, market participation, certificate transfer, and ongoing contractual administration. Together, these requirements are intended to preserve the integrity of the VPPA structure, prevent double counting of renewable attributes, and ensure that VPPAs remain non-tradable, bilateral arrangements distinct from market-traded financial products. The principal requirements are discussed below.
a) Essential features: Under Clause 5, the electricity must be sold at the Settlement Price for physical delivery; the RECs received must be transferred to the consumer or DC for renewable purchase obligation (“RPO”) or RCO compliance; the contract must be a bilateral OTC contract that is non-tradable and non-transferable; and it must run for a minimum of one year.
b) Registration: The contracted capacity is eligible for RECs only upon registration under the CERC (Terms and Conditions for Renewable Energy Certificates for Renewable Energy Generation) Regulations, 2022 (“REC Regulations”), in terms of Clause 8. The registry, accounting and monitoring are administered by Grid Controller of India Limited (“Grid India”).
c) Choice of market segment: The electricity component must be sold through segments other than the Green Day Ahead Market (“GDAM”) and the Green Term Ahead Market (“GTAM”), since sale through the green segments disqualifies the energy from REC issuance.
d) Undertaking against double counting: The REGS must furnish an undertaking to the REC registry in respect of the contracted capacity, to prevent duplicate accounting.
e) Transfer and extinguishment: Regulation 14A of the amended REC Regulations[14] deems the RECs transferred to the consumer or DC; receipt must be communicated to the registry, and the Central Agency extinguishes the certificates upon use. Surplus RECs may be carried forward but not sold on power exchanges or through traders.
f) Absolute non-transferability: RECs linked to a VPPA cannot be assigned to affiliates, group companies, lenders, or speculators, including for financing purposes, and registration under global attribute schemes is barred. On a change in ownership of the REGS, its obligations transfer in accordance with applicable law.
g) Commercial terms: Pricing, settlement, payment security, risk mitigation, and taxation follow the mutually agreed terms and applicable law. Disputes are to be settled between the parties in terms of the contract, with CERC supplying the procedural framework rather than adjudicating.
Why This Matters Now: VPPAs and India's Steepening RCO Curve
The Guidelines did not arrive in a vacuum and boards evaluating whether to use a VPPA should understand the regulatory current now pulling in their favour. India's renewable energy build-out is no longer a policy aspiration; it is a measurable, accelerating fact. Total non-fossil generation capacity stood at 283.46 GW as of March 31, 2026, of which 274.68 GW was renewable energy, against the Panchamrit target of 500 GW of non-fossil capacity by 2030 announced at COP26. That build-out has to find buyers and a large and growing share of demand is not discretionary; it is compliance-driven.
The Energy Conservation (Amendment) Act, 2022 brought the Renewable Consumption Obligation (“RCO”) within statutory purview, and the Ministry of Power's trajectory notification, first issued on October 20, 2023, and superseded on September 27, 2025, requires Designated Consumers across twenty-six energy-intensive sectors, from cement, steel, and aluminium to textiles, chemicals, ports, hotels, and airports, to source a rising minimum share of their electricity consumption from eligible non-fossil sources.[16] That share is not static. Under the current trajectory, it climbs sharply over the balance of the decade:
Metric | FY 2024-25 | FY 2025-26 | FY 2026-27 | FY 2027-28 | FY 2028-29 | FY 2029-30 |
National RCO Target | 29.91% | 33.01% | 35.95% | 38.81% | 41.36% | 43.33% |
CERC RCO Buyout Price (INR /MWh) | 347 | 347 | 364 | 382 | 401 | 421 |
Source: Bureau of Energy Efficiency, Ministry of Power.
For a Designated Consumer running a cement plant, a textile mill, or an airport on a captive or open-access connection, that trajectory is not an abstraction; it is a rising cost of non-compliance that treasury and sustainability teams will be modelling for the rest of the decade.
Crucially, the Ministry of Power's amended RCO notification expressly recognises the VPPA as a standalone mode of RCO compliance, alongside own generation, DISCOM requisition, consumption of green hydrogen or green ammonia, purchase or self-retention of RECs, and the RCO Buyout Mechanism. CERC's buyout price fixed at INR 347 per MWh through FY 2025-26 and rising to INR 421 per MWh by FY 2029-30, gives corporates and generators a public, predictable reference point when negotiating VPPA strike prices, since it approximates the cost of walking away from the RE market altogether.
Viewed in this context, the timing of the Guidelines is unsurprising. They arrive at a point when India's renewable energy supply is expanding rapidly, while RCO obligations are becoming progressively more demanding for Designated Consumers. At the same time, the regulatory framework now expressly recognises VPPAs as a distinct route to RCO compliance. The result is a mechanism that enables corporate consumers to support renewable energy projects, secure renewable attributes through RECs, and manage compliance obligations without the operational constraints associated with traditional physical power procurement arrangements.